Construction Updates October 19

For the week of October 19th to October 23rd–
· Crews will be working from Main Street to Cherry Street on WIS 22.
o WIS 22 will be open to local traffic from South Main Street to Cherry Street but will be limited, due to construction activity along the corridor.
o Both Cherry Street and Central Avenue will be closed to WIS 22 from the east while the intersections achieves proper cure time and strengths.
o Once both Cherry Street and Central Avenue achieve proper cure, both streets will reopen to WIS 22 from the east. At which time, Caldwell Avenue will be closed to complete the remaining concrete pavement gaps.
o Vinton Construction will be forming and pouring the intersections of Caldwell Avenue and Union Street.
o Vinton Construction will continue with concrete patch work from Cherry Street to Highland Drive. Traffic will be reduced to one lane in each direction on the center lanes.
o Martell Construction will continue pouring sidewalks along the south and north side of the roadway from Union Street to Cherry Street.
· The schedule is subject to change due to unforeseen conflicts and/or weather events.
· Traffic control measure should ONLY be moved by authorized personnel.