For the week of July 27h to July 31st, –
- Crews will be working from Main Street to East Highland Drive.
o Martell Construction will continue to pour sidewalk along both sides of WIS 22 from Main Street to the East Highland Drive. They will be completing sidewalk ramps at various intersections and continuing to pour driveways along both sides of WIS 22. Residence will need to anticipate temporary driveway closures during each individual driveway pour.
o The railroad crossing signals will be installed between Monroe Street and Quincy Street.
o Peters Concrete will continue to grade for sidewalks. Crews will start to place topsoil between the curb and sidewalk as well as on the backsides of the sidewalk.
o Van Buren Street, Paul Street, Grove Street, Columbia Street, Chestnut Street will be opened to allow for local traffic only. Jefferson Street, Adams Street, Washington Street and Franklin Street will be opened to allow for local traffic only in the later part of the week after strengths have been achieved for the concrete colored crosswalks. All side streets will still be signed as “Road Closed to Through Traffic”.
o Double D will be onsite starting to landscape various locations from Main Street to East Highland Drive.
o NEA will be in at the end of the week to pave side street tie ins and driveways from Main Street to East Highland Drive.
o Bodart Electric will be in to install concrete bases for street lighting between Franklin Street and Adams Street.
- The schedule is subject to change due to unforeseen conflicts and/or weather events.”
- We encourage the businesses in the downtown section to attend this Friday’s (JULY 24) meeting at 10:00 AM in City Hall to discuss in further detail scheduled work from Main Street to Cherry Street.