Highway 22 street construction in Oconto Falls:
Paving started today on the west half of Chestnut Avenue, beginning at the the East Highland Drive intersection. Paving was scheduled to continue past Monroe Street, and the pavement will take about a week to cure so the street will be closed. However, the Jackson Street intersection will be open.
Sidewalk work was scheduled to start on Friday on Chestnut Avenue, but contractors don’t plan to place top soil, seed or mulch yet.
Crews will continue their work on storm sewer, grading and graveling of Chestnut Avenue to South Main Street.