Construction Update August 3rd

Crews will be working from Main Street to East Highland Drive.

o Peters Concrete will continue to grade for landscaping. Crews will start to place topsoil between the curb and sidewalk as well as on the backsides of the sidewalk.

o Double D Landscaping will continue to complete landscaping from Main Street to East Highland Drive in the terrace areas and back side of sidewalks. They will also start installing street signs throughout the project limits.

o Northeast Asphalt will start paving asphalt tie in locations at all side streets from Main Street to East Highland Drive. They will also complete asphalt driveways and parking lots.

o Brickline will be onsite completing pavement marking from Main Street to East Highland Drive.

o All intersections from Main Street to East Highland Drive will be opened to allow for local traffic only. There will be partial closures on these intersections during asphalt tie ins and painting on crosswalk pavement markings. All side streets will still be signed as “Road Closed to Through Traffic”.

· The schedule is subject to change due to unforeseen conflicts and/or weather events.